Valley Village build-outs that route condensate, protect wet walls and seal restroom floors, drawn for LADBS plan check and broken out in a written quote.
Every cooling coil added to a Valley Village suite pulls water out of the air, and the build-out has to carry that water to an approved drain. We set the slope of each condensate line, decide whether a pump is needed, and add a secondary pan or overflow switch under units that sit above finished ceilings. Sinks and restroom floors get the same thinking, so water stays inside pipes, pans and membranes.
Condensate lines and overflow protection
A gravity condensate line needs continuous fall to its termination, and a tight plenum may leave no room for it. Where that happens, a small pump lifts the water, wired to a float switch that stops the cooling unit if the pump fails. The line is insulated where it runs through warm, humid space such as an unconditioned plenum or an attic, because a cold pipe sweats there. Units above finished ceilings sit over a secondary pan with its own switch. Termination points are drawn on the mechanical sheets so plan check sees where the water ends up.
Wet walls, floors and shutoffs
A break-room sink wall is sheathed in water-resistant board, finished with a sealed backsplash and backed by solid blocking for the fixture. Restroom floors take a waterproof membrane turned up the wall, plus a floor drain and trap primer where the plans call for them. Isolation valves for each new fixture group are placed where a tenant can reach them, with access panels as needed. Finishes that tolerate wet mopping, such as sealed tile or sheet vinyl, are priced as separate lines. New supply and drain piping is tested before any wall is closed.
About our tenant improvements workEverything we build in Valley Village
Tenant Improvements in Valley Village: questions
Yes. We price to the letter and to the building's contractor rules, with landlord-funded work shown on its own lines. Plumbing ties into building risers, and shutting off water affects other tenants, so if the letter limits when that can happen, those windows go into our schedule before the plumber is booked.
A plumber handles sinks, restroom fixtures and drains, and a mechanical contractor installs cooling units with their condensate lines and pumps. Framers, drywall finishers, an electrician and a low-voltage cabler work around them. A sprinkler fitter joins if ceilings change, and tile setters, flooring installers and painters complete the suite.
Plan approval from LADBS and the landlord's approval of the plans decide the start. Equipment and fixtures with long order times can stall the rough-in, and plumbing must pass its test before walls close. Inspections set the pace from there. Our written schedule lists every gate with a date, so you can test the lease date against how the work will actually run.
Tenant Improvements in other cities