New Construction in San Gabriel
New houses in San Gabriel where a house already stands: utility releases, the asbestos survey, demolition and clearing in the order permits require. Licensed.
Where an older house still stands on a San Gabriel lot, the build begins by taking its services away. Gas, power and water are cut off by each provider at its own equipment, the sewer is capped as the city directs, and an asbestos survey goes to the regional air district with a notice of the planned work. The demolition permit follows those papers. If the ground slopes, clearing is also the first chance to measure the true grade under the old house.
Releases and the survey
Each utility schedules its own crew. The gas company pulls the meter and caps the line, the electric utility removes the service drop or disconnects it at the pole, and the water provider locks or removes the meter. Each sends a written release, and the building department checks for all of them before demolition can start. The asbestos survey runs in parallel, and anything it finds is taken out by a licensed abatement contractor and cleared before a machine touches the walls. We request every release together, so a slow reply from one provider does not hold back the rest.
From rubble to a staked footprint
Demolition takes the house down to its slab, then the slab, footings, buried lines and large roots come out. Under the state's green building rules, much of that debris goes to recycling. The soils engineer walks the open ground and marks any soft spots or old fill for removal. A surveyor then sets offset stakes for the new corners and a benchmark for depth. Footing trenches are dug to those marks, the engineer signs off the bottoms, and the city inspects the reinforcing steel before any concrete truck is called.
About our new construction workEverything we build in San Gabriel
New Construction in San Gabriel: questions
Order the boundary and topographic survey and the soils report alongside the demolition plan, since borings reach more of the lot once the house is gone. The survey should also locate the sewer lateral and the water service. A title report lists easements, and an arborist letter is needed if a protected tree stands near the work.
Taking the old house down is the first job that needs room. An excavator arrives on a trailer and debris leaves by the truckload, so a narrow drive means a smaller machine and more trips. Once the lot is clear, that same opening serves concrete and lumber. Demolition access and construction access sit on separate lines of the quote.
Yes. Architects seldom draw the demolition, the utility releases or the abatement, so we add them from our own site visit and note what we measured. The new house is priced from the plans, structural calculations and soils report, trade by trade, and the two parts stay on separate pages of the quote.