New houses in Rolling Hills Estates started in order: fencing, temporary power, a stabilized entry and erosion controls before the first cut, then closed out.
Before any ground is cut for a new Rolling Hills Estates house, the site itself is set up. A fence goes around the work area, a temporary power pole is set where the utility approves it, and a gravel pad at the driveway keeps trucks from tracking soil into the street. If the lot slopes, fiber rolls and silt fence go in below the work before grading begins, so the first rain finds them in place.
Setting up before the first cut
Trees that stay are fenced out at their root zones. A portable toilet, a storage container and a materials area are placed where they will not block the pad or the pump truck later. Stockpiles of soil get covered, and inlets downstream are protected so sediment does not reach the storm drain. The inspector may check the erosion controls before grading is approved, so we have them in before the first excavator arrives. Neighbors' walls near the work are noted on the site plan, so equipment stays clear of them.
Closing the site in order
The end of the job runs in sequence too. The utility's service has to be energized before the temporary pole comes down, and final grading and yard drains go in after exterior work, so heavy equipment does not crush new pipe. Landscaping that holds a slope is planted before the erosion controls are removed. Final inspection comes after the soils engineer's grading report and any special inspection reports are on file, and only then do the fences and the gravel entry leave the site.
About our new construction workEverything we build in Rolling Hills Estates
New Construction in Rolling Hills Estates: questions
First come a topographic survey and a geotechnical report, joined by a geology report if the parcel slopes. The reviewer may also want an erosion control plan for the construction period and a drainage plan for the finished lot. Utility disconnects come before an existing house is taken down.
Where the approach is tight, trucks carry partial loads and make extra runs. A steep approach adds a pump line or a crane, and soil leaving the site travels the same drive. Room for the storage container and the materials area matters too, since a site with nowhere to stage needs timed deliveries. We price the methods we expect to use.
Yes, when the architect's sheets come with structural calculations, a soils report and, on a sloping parcel, the geology findings. The price is broken out by phase, starting with site setup and erosion control and ending with final grading and closeout. Open design choices become allowances with their assumptions written beside them.