New Construction in Reseda run in the order LADBS inspects it: footings and under-slab pipe first, then rough trades, then the frame check before insulation.
On a new Reseda house, nothing above the slab starts until the ground below it is settled. The soils engineer signs off on the bottom of every footing trench, and LADBS looks at the forms, the steel and the hold-down bolts before any concrete arrives. Pipe that runs under the slab is tested in the open trench first. If the lot slopes, a stepped footing brings a check at each step, and the schedule is built backward from those visits.
Under the slab, then the walls
Sewer and water lines that pass beneath the floor are laid and tested while the trench is still open, and the inspector signs them before gravel and the vapor retarder go down. The pour follows. Once walls stand, plywood shear panels and the roof deck each get a nailing inspection, since both disappear under building paper and roofing. Window and door flashing is looked at around the same time. Missing a visit here means pulling material back off later, so each one is booked as soon as the work it covers is ready.
Rough trades before the frame sign-off
Plumbing, electrical and mechanical rough-in come next, each with its own inspection: drains held under a column of water, supply lines under pressure, boxes and cable left open, ducts sealed and strapped. Only after all three pass does the inspector make the frame inspection, because every hole a plumber or electrician bores through a stud or joist has to be seen before it is buried. Insulation goes in after that, a HERS rater may test the ducts and the air sealing, and drywall nailing is inspected before taping starts.
About our new construction workEverything we build in Reseda
New Construction in Reseda: questions
The surveyor fixes the property corners and the existing grades first. Borings give the soils engineer what is needed to set footing depth and bearing values. The energy compliance report is drafted alongside the design, because it lists the insulation and equipment the inspectors check later. If the building pad needs reshaping, a grading plan is added to the set.
Each inspection stage brings its own deliveries: concrete for the footings, lumber and sheathing for the frame, then insulation and drywall. A wide frontage lets those trucks unload beside the house. On a narrow lot, loads are split and timed around the trades already working, and a lift may carry upper floor material. Those costs are written into the quote phase by phase.
Yes. We read the architectural and structural sheets together with the energy report, since that report fixes window ratings, insulation and equipment. Each phase gets its own price, from grading through finishes. Where the drawings leave a detail open, such as a hold-down or a duct route, we note the assumption so it can be settled before plan check.